Complete Condo Remodel in Austin

The bathroom, IKEA kitchen, vinyl plank flooring and finish work across this condo were coordinated as one renovation.

Location
Austin, TX
Original labor scope
$16,500
Original planned schedule
12 working days
Materials
Purchased separately
The renovated living area and finished surfaces.
Completed condo
The renovated living area and finished surfaces.

The Goal, Our Approach and the Result

The goal

The owners wanted a kitchen and bath update alongside new floors, wall repairs, doors and interior finishes. Those scopes had to fit within one work plan.

Our approach

We coordinated the work in stages under the original labor agreement. The owner purchased materials separately, and new requests and concealed-condition repairs were handled outside the original scope.

The result

The completed kitchen, bath and adjoining living spaces were brought together with new flooring, smooth painted surfaces and coordinated trim and fireplace finishes.

Project Photos

Before

One of the original rooms before the renovation.
Before renovation
One of the original rooms before the renovation.
Original condo interior before the complete renovation, photo 2
Before · Photo 2
Original condo interior before the complete renovation, photo 3
Before · Photo 3
Original condo interior before the complete renovation, photo 4
Before · Photo 4
Original condo interior before the complete renovation, photo 5
Before · Photo 5
Adjoining interior conditions before the agreed work.
Before renovation
Adjoining interior conditions before the agreed work.
Original condo interior before the complete renovation, photo 7
Before · Photo 7

During the Work

Upper IKEA cabinets being fitted within this condo scope.
During kitchen installation
Upper IKEA cabinets being fitted within this condo scope.

After

A finished area after the condo renovation.
Completed interior
A finished area after the condo renovation.
Completed Austin condo remodel by Kir Remodeling, photo 2
After · Photo 2
Completed Austin condo remodel by Kir Remodeling, photo 3
After · Photo 3
Finish details at the end of the documented renovation.
Completed interior
Finish details at the end of the documented renovation.
Completed Austin condo remodel by Kir Remodeling, photo 5
After · Photo 5
Completed Austin condo remodel by Kir Remodeling, photo 6
After · Photo 6
Completed Austin condo remodel by Kir Remodeling, photo 7
After · Photo 7
Completed Austin condo remodel by Kir Remodeling, photo 8
After · Photo 8
Completed Austin condo remodel by Kir Remodeling, photo 9
After · Photo 9
Completed Austin condo remodel by Kir Remodeling, photo 10
After · Photo 10
Completed Austin condo remodel by Kir Remodeling, photo 11
After · Photo 11
Another view of the completed interior.
Completed interior
Another view of the completed interior.
Completed Austin condo remodel by Kir Remodeling, photo 13
After · Photo 13
Completed Austin condo remodel by Kir Remodeling, photo 15
After · Photo 15

Project Video

What the Work Included

Bathroom

Rebuilt the room with a tub, wet-area preparation, wall and floor tile, fixtures, lighting and finish details.

IKEA kitchen

Assembled and installed cabinets, provided the agreed countertop support and coordinated sink, faucet and disposal connections.

Flooring

Prepared the agreed living areas for new LVP and completed the transitions.

Walls and interior paint

Patched damaged areas, prepared drywall and painted the agreed surfaces.

Doors, windows and trim

Completed door and baseboard work, interior sills and returns, caulking and adjustments.

Fireplace and final connections

Finished the fireplace tile and shelf and coordinated the agreed fixture and localized electrical work.

Planning a Similar Project?

The $16,500 figure is the original labor agreement. Twelve working days was the original plan. The owner purchased materials separately, and later extras and concealed-condition repairs were outside the original scope.

Decisions to Make Before a Similar Remodel

Stages and payment

The original plan used agreed work stages. The written agreement defined when each payment was due.

Materials

The homeowner purchased materials separately. Quantities, delivery and product readiness needed to fit the schedule.

Added or concealed work

Client-requested changes and repairs discovered during work were addressed outside the original scope.

Initial project review

Tell Kirill about your home.

Tell Kirill what you’d like to change or build. He’ll follow up to discuss your project and whether a walkthrough makes sense.

Add project details (optional)